Construction of the Temporary Sewage Treatment Plant Construction of Pad Footing August 2019 - May 2020 Superstructure Construction Construction of Equalization Tank by Design for Manufacture & Assembly (DfMA) Construction of Equalization Tank by Design for Manufacture & Assembly (DfMA) Construction of Moving Bed Biofilm Reactor (MBBR) by DfMA August 2019 - May 2020 Construction of Moving Bed Biofilm Reactor (MBBR) by DfMA Erection of Plant Equipment In Progress Temporary Sewage Treatment Plant Commissioning Ceremony Temporary Sewage Treatment Plant Commissioning Ceremony | Early 2019 – Mid 2020 | Commenced Operation in July 2020 |
Construction of the New Submarine Outfall August 2020 Drilling Operation at Landside Drilling Operation at Landside March - October 2021 Drilling Operation at Seaside Drilling Operation at Seaside Pipes Butt-fusion Jointing February 2022 Pipe Installation at Seaside Pipe Installation at Seaside Pipe Installation at Seaside Pipe Installation at Seaside | Mid 2020 – Early 2022 | Installation Completed in February 2022 |
Gravity Sewers Laying in Sha Tau Kok Town December 2020 Excavation and Lateral Support Works Excavation and Lateral Support Works August 2021 Construction of Working Pit Construction of Working Pit January - March 2022 Drilling and Sewage Pipes Laying inside the Pit Drilling and Sewage Pipes Laying inside the Pit Drilling and Sewage Pipes Laying inside the Pit Drilling and Sewage Pipes Laying inside the Pit April - August 2022 Excavation and Lateral Support Works Excavation and Lateral Support Works November 2022 Laying of Sewage Pipe at Sha Tau Kok Road January 2023 Sewage Pipe Laying by Trenchless Method in Sha Tau Kok Town February 2023 Manhole Construction in Sha Tau Kok Town April 2023 Sewage Pipe Laying by Trenchless Method in Sha Tau Kok Town May 2023 Completion of Sleeve Pipe Installation by Trenchless Method at Access Road July 2023 Sewerage Pipe Installation at Access Road August 2023 Completion of Road Resurfacing Works at Shun Hing Street and Shun Lung Street October 2023 Construction of Remaining Sewerage Works at Verge Area near Sha Tau Kok Recreation Ground January 2024 Completion of Sewerage Works at Sha Tau Kok Town | Early 2019 – Late 2024 | Installation completed in October 2024 |
Provision of Village Sewerage in Tong To October 2020 Non-Destructive Cable Detection Works and Trial Pit Excavation January 2021 Gravity Sewers Laying at Lo Wai September 2021 Pipe Laying by Trenchless Technique January - March 2022 Sewage Pipe Laying by Trenchless Method January - March 2022 Sewage Pipe Laying by Trenchless Method April - August 2022 Sewage Pipe Laying by Open Trenching Method Sewage Pipe Laying by Trenchless Method September 2022 Construction of Sewerage Works in Tong To Village October 2022 Laying of Sewage Pipe in Tong To Village September 2023年 Completion of Sewerage Works at Tong To Village | Early 2020 - Late 2023 | Installation completed in September 2023 |
Construction of the New Sha Tau Kok Sewage Treatment Works March - October 2021 Excavation and Lateral Support Works Excavation and Lateral Support Works January - March 2022 Excavation and Lateral Support Works Excavation and Lateral Support Works January - March 2022 Excavation and Lateral Support Works Excavation and Lateral Support Works December 2022 Installation of Slab Segments by DfMA Method January 2023 DfMA(MEP) Fabrication Yard - Service Rack Installation in Progress March 2023 Installation of Wall Segments by DfMA Method March 2023 Inspection on DfMA Segments in Fabrication Yard in Mainland April 2023 Updating the fabrication status by Smart tag (RFID) system April 2023 DfMA(MEP) Fabrication Yard - Inspection of Pump Skid Installation June 2023 Installation of MVAC Air Duct at Pump Area at New STW July 2023年 Delivery of DfMA Pump Skids to Pump Area at New STW Installation of Wall Segments by DfMA Method August 2023 Off-site Inspection for LVSB cabinets fabrication September 2023 Assembly Work of Double-deck DfMA Service Racks at Fabrication Yard October 2023 Installation of FS Pumps in FS & Sprinkler Pump Room at New STW February 2024 Installation of E&M Equipment at New STW March 2024 Diffuser Installation in Aerobic Tank at New STW March 2024 Skylight Installation at New STW March 2024 LVSB Temperature Rise Test April 2024 Monorail Cranes Installation Sludge Thickener Installation June 2024 Biothickling Filter Installation July 2024 Cable termination in MCC Room Torque test for diffuser supports in the Aerobic Tank of the New STW. Power energization in LVSB Room of the New STW August 2024 Membrane Air Header Installation August 2024 Extraction Fan Installation September 2024 Membrane Filter Installation October 2024 Underground pipework installation November 2024 Air Blower Testing and commissioning Air Blower Testing and commissioning Tile installation at New STW December 2024 Commencement of Plant Commissioning Bioreactor Activated Sludge Transfer SAT of FS pump of New STW Completion of Plant Commissioning Installation of FRP platform at New STW | Mid 2020 – Early 2025 | In Progress |
Provision of Village Sewerage in Tsoi Yuen Kok Village September 2022 Inspection Pitting Work in Tsoi Yuen Kok Village January 2024 Provision of Village Sewerage in Tsoi Yuen Kok Village March 2024 Provision of Village Sewerage in Tsoi Yuen Kok Village | Early 2025 | Installation completed in January 2025 |