Progress Photos Planned Construction Period Works Progress
Construction of the Temporary Sewage Treatment Plant Early 2019 – Mid 2020 Commenced Operation in July 2020
Construction of the New Submarine Outfall Mid 2020 – Early 2022 Installation Completed in February 2022
Gravity Sewers Laying in Sha Tau Kok Town Early 2019 – Mid 2024 In Progress
Provision of Village Sewerage in Tong To Early 2020 - Late 2023 Installation completed in September 2023
Construction of the New Sha Tau Kok Sewage Treatment Works Mid 2020 – Early 2025 In Progress
Provision of Village Sewerage in Tsoi Yuen Kok Village Mid 2024 In Progess